BlueDoorInvestor Toolkit
New deal
No saved flips yet — hit “Save deal” to keep one here.
Max offer
$785,928
for $75,000 profit
Net profit
$147,542
at $720,000
Profit floor
$75,000
$72,542 of headroom
ROI · annual
79.3%
144.1% annualized
Peak cash
$185,994
hard money
Purchase
$720,000
$497/sf
ARV — base
$1,275,000
$879/sf
Rehab — base
$220,000
$152/sf
Gross spread
43.5%
target 25–30%
All-in cost
$1,039,594
$717/sf · 201 days
Each section keeps its headline figure when shut.
Property & deal1,450 sf · 3bd / 2ba
City—Swings hugely by city — most of San Mateo and Santa Clara sit at the county floor; Oakland and Berkeley do not.
Square feet—Living area from the tax record. Every per-foot figure divides by it.
Beds / full baths / half
—Drives scope-of-work quantities — a 4/3 prices three showers, not one.
Stories / garage bays
—Estimates the foundation perimeter for seismic work and gutters.
Year built—Pre-1980 assume asbestos and lead; pre-1950 assume knob-and-tube and an unbolted foundation.
Purchase & after-repair value$555,000 spread · 43.5%
Purchase price$497/sf$497/sf$720,00070% rule says $672,500; your own underwrite says $785,928.
ARV — low$828/sf$828/sf$1,200,000What it sells for in a slow month with a picky appraiser.
ARV — base$879/sf$879/sf$1,275,000Closed comps within half a mile and 90 days, adjusted to your finish.
ARV — high$924/sf$924/sf$1,340,000Top of the range if the finish lands. Never underwrite to it.
Gross spread at base ARV43.5%$555,00043.5%$555,000Target 25–30% of ARV. You are at 43.5% — comfortably in range.
Rehab budget$220,000 · manual
Bay Area pricing: cosmetic $90–160/sf, full gut $200–350/sf. Yours is $152/sf at base — cosmetic territory. Build it on the Scope of Work tab and push it here.
Rehab — low$124/sf$124/sf$180,000Everything goes right: no dry rot, no surprises behind the walls.
Rehab — base$152/sf$152/sf$220,000What you would tell a partner the job costs. The deal lives on it.
Rehab — high$197/sf$197/sf$285,000You open the walls and find why it was cheap. Honest case pre-1950.
Timeline201 days
Every extra day costs holding and interest at once. Bay Area flips run 150–240 days door to door. Yours is 201 — normal.
Rehab durationdaysdays4.9 moFold permits in. Bay Area plan check adds 60–120 days before a shovel moves.
Days on marketdaysdays0.7 moList to accepted offer. Bay Area ran 15–25 days through 2026.
Escrow perioddaysdays1.0 moAccepted offer to close. 21–30 days standard; a cash buyer can do 14.
Schedule overrundaysdays0.0 moAdd days to see what a slip costs. The cheapest stress test here.
Total hold period6.6 mo201 days6.6 mo201 daysA 30-day slip costs roughly $7,656.
Acquisition costs$22,925
Seller provided disclosure package—California sellers normally deliver TDS, SPQ, NHD and the pest, home and roof reports before offers. Switching this on zeroes the lines it covers.
Buy-side commission%%$18,000What you pay a buyer's agent to acquire. If you represent yourself it is income, not a cost.
Escrow fee — buy side$1,800About $2 per $1,000 plus a base fee. Each side pays its own.
Lender's title policy$1,400Lender-required and buyer-paid. Drops to $0 all cash.
County recording$225Fixed county charge. Barely moves with price.
General home inspectionseller$0$500–800 for your own. Seller’s package normally covers it.
Pest / termite inspectionseller$0$350–500, almost always in the seller’s package.
Sewer lateral video scope$350Worth it anyway — a failed lateral is $15–30k and four cities demand a certificate.
Foundation / structuralseller$0$600–1,000. Order on pre-1950 or any visible cracking.
Roof inspectionseller$0$300–450, usually in the seller’s package.
Appraisal / BPO$900$700–1,100, lender-required and buyer-paid. $0 all cash.
Wire, notary, courier, misc$250Small fixed escrow charges.
Total acquisition3.2%$22,9253.2%$22,925Loan points are not here — they live under Financing.
Holding costs$12,118 · $905/mo
Live-in flip—You move in, hold past two years, then sell. The months you live there are not vacant, so an empty house's costs never happen — and the housing you would have paid for anyway is not a cost of the deal.
Levied property tax rate%%$4,9531% Prop 13 base plus local bonds. A published “effective rate” understates this by a third.
Prior assessed value—From the county assessor. Only used to break out the supplemental bill.
Builder's risk insurance
$1,189Covers the structure while it is open. 1–3% of rehab, or $150–300/mo.
Monthly operating — enter $/mo, total over the hold at right
Vacant dwelling insurance$/mo$/mo$2,311$250–450/mo and not optional — an HO-3 voids once unoccupied.
Electricity$/mo$/mo$594Construction power runs well above a lived-in bill.
Water$/mo$/mo$396Keep it on for the trades and for landscaping.
Gas$/mo$/mo$264Often off during a gut, back on for staging.
Trash$/mo$/mo$198Separate from demo dumpsters, which sit in rehab.
Landscaping & site upkeep$/mo$/mo$991An overgrown yard reads as distressed. Cheap insurance.
Security — alarm & cameras$/mo$/mo$561Copper theft and squatting are real on a vacant house.
HOA dues$/mo$/mo$0Condos and PUDs only. Check for a special assessment first.
Entity, bookkeeping, misc$/mo$/mo$660LLC franchise tax, bookkeeping, bank fees.
Total over 6.6 months$12,118$12,1181.0% of ARV. Runs whether or not anyone is working on the house.
Selling costs$87,863 · 6.9% of sale
All-in Bay Area selling costs run 7–9% of sale price. Yours are 6.9% — in range. If you list it yourself, that commission is income to you, not a cost.
Listing commission%%$31,8752.5% standard. Your own listing side is income, not an expense.
Buyer agent commission%%$31,875Negotiable since the NAR settlement, but 2.5% still gets it shown.
City transfer tax paid by
$1,403Local custom varies. Pick a city above to pre-fill it.
Escrow fee — sell side$2,200Your half of escrow on the way out.
Owner's title policy$3,400Seller-paid by custom. About $2.50–3 per $1,000 of sale.
County recording — sell side$225Fixed county charge.
Natural hazard disclosure report$150Required on every CA residential sale. Fixed vendor fee.
Home warranty$600Optional one-year buyer policy. Cheap objection remover.
Staging — setup$4,500$4–6k to install. Highest-return line in the selling budget.
Staging — per month$/mo$/mo$2,011$1–1.5k/mo through days on market plus escrow.
Retrofit compliance$3,250Lateral certificate, water heater strapping, alarms — varies by city.
Seller concessions%%$6,375Credits after the buyer’s inspection. 0.5% is light; 1% safer on an older house.
CA 3.33% withholding—Escrow withholds it at close and credits it on your return. Moves cash timing, never profit.
Total selling costs6.9%$87,8636.9%$87,863Recomputed per ARV scenario — most of these are percentages of sale.
Financing$64,552 · hard money
Hard money funds the rehab in draws; conventional funds only the purchase; all cash ties up every dollar but pays no interest at all.
Instrument
—Switching swaps the input set rather than reinterpreting it.
Loan-to-cost on purchase%%$633,600Bay Area hard money runs 85–90% of purchase.
Rehab financed%%$220,000Usually 100%, released in draws as work is inspected.
Interest rate%%$44,5809.5–12% in 2026. Interest-only on the drawn balance.
Points%%$17,0721.5–3 points at close on purchase loan plus rehab holdback.
Lender fees$1,500Underwriting, doc prep, legal. $1–2k typical.
Draws / fee each
$1,400$250–500 each plus an inspection delay. Fewer, larger draws cost less.
Minimum interestmomo—Most lenders guarantee 3–6 months even if you pay off early.
Extension fee%%$0Charged when the overrun above is more than zero. 0.5–1 point.
Total financing cost$64,552$64,5525.1% of ARV — after rehab, usually the second-largest cost.
Loan at close$633,600$633,600Funded at close, before any rehab draw.
Down payment$86,400$86,400Purchase price less the loan.
Cash needed for rehab$0$0Only the unfinanced share; the lender reimburses the rest by draw.
Peak cash out of pocket$185,994$185,994The number that decides whether you can do this deal at all.
Clears your floor
Base case beats your minimum profit with room for the ARV to slip.
Max offer
$785,928
for $75,000 profit
Net profit
$147,542
11.6% of ARV
Profit floor
$75,000
$72,542 of headroom
ROI on cash
79.3%
$185,994 invested
Annualized
144.1%
201 days hold
Profit floor$75,000
Minimum profitthe walk-away number$75,000What the deal has to clear for you to do it. Sets the verdict above, the max offer, and where the grid below turns green.
The 70% rule is stricter than your own numbers by $113,428. It assumes financing and selling costs that Bay Area price points don't match, so trust your MAO.
Net profitARV across · rehab down
Rehab ↓   ARV →$1,186,000$818/sf$1,214,000$837/sf$1,242,000$857/sf$1,270,000$876/sf$1,298,000$895/sf$1,326,000$914/sf$1,354,000$934/sf
$169,500$117/sf$117k$143k$170k$196k$223k$249k$275k
$190,500$131/sf$94.7k$121k$148k$174k$200k$227k$253k
$211,500$146/sf$72.5k$98.9k$125k$152k$178k$205k$231k
$232,500$160/sf$50.3k$76.8k$103k$130k$156k$182k$209k
$253,500$175/sf$28.2k$54.6k$81.0k$107k$134k$160k$187k
$274,500$189/sf$6.0k$32.4k$58.8k$85.3k$112k$138k$165k
$295,500$204/sf($16.2k)$10.2k$36.6k$63.1k$89.5k$116k$142k
Loses moneyUnder your $75,000 floorClears the floorYour budget at base ARV

Axes span your low-to-high ARV and rehab scenarios with 10% headroom past each end. Purchase price ($720,000), timeline (201 days), and financing are held fixed.

Deal modelrehab budget $220,000
ScenarioARV low
$1,200,000
ARV base
$1,275,000
ARV high
$1,340,000
% of sale
Scope & timeline
Rehab budget$220,000$220,000$220,00017.3%
Total hold period — months6.66.66.6
Sale proceeds
Gross sale price (ARV)$1,200,000$1,275,000$1,340,000100.0%
Less selling costs($83,656)($87,863)($91,510)6.9%
Net sale proceeds$1,116,344$1,187,137$1,248,49093.1%
Cost into the deal
Purchase price($720,000)($720,000)($720,000)56.5%
Acquisition costs($22,925)($22,925)($22,925)1.8%
Rehab budget($220,000)($220,000)($220,000)17.3%
Holding costs($12,118)($12,118)($12,118)1.0%
Financing cost($64,552)($64,552)($64,552)5.1%
Result
Net profit / (loss)$76,750$147,542$208,89611.6%
Returns
Return on cash41.3%79.3%112.3%
Annualized return75.0%144.1%204.1%
Margin — % of ARV6.4%11.6%15.6%
Capital
Cash to close$127,897$127,897$127,897
Cash during hold$58,097$58,097$58,097
Peak cash out of pocket$185,994$185,994$185,994
Loan payoff at sale$853,600$853,600$853,600
Cash back at close$262,744$333,537$394,890
Rehab estimate
$0
$0/sf
Tasks scoped
0
across 21 spaces
Not yet scoped
21
spaces untouched
Often missed
21
still unscoped
21 spaces have nothing scopedKitchen · Bathroom 1 · Bathroom 2 · Bedroom 1 · Bedroom 2 · Bedroom 3 · Living Room · Dining Room …. Set each to Skip once you have decided it genuinely needs nothing — forgetting a space is the single biggest source of a blown rehab budget.
Commonly missed and not yet scopedRange hood and exterior venting (Kitchen) · Dedicated circuits and GFCI (Kitchen) · Exhaust fan vented to exterior (Bathroom 1) · Exhaust fan vented to exterior (Bathroom 2) · Dryer vent to exterior (Laundry) · Sheathing replacement (Roof & Gutters) · and 15 more. These are the lines that turn up after demolition rather than before an offer.
Propertydrives every room below
Square feet—
Bedrooms—
Full baths—
Half baths—
Stories—
Garage bays—
▶Kitchen sf0 / 18—
TaskQtyEst. priceCost
Demo and haul-outea
—
Cabinets — stock, installedlf
—
Cabinets — semi-custom, installedlf
—
Reface or repaint existing cabinetslf
—
Island — cabinetry and topea
—
Countertops — quartz or slabsf
—
Tile backsplashea
—
Sink and faucetea
—
Appliance packageea
—
Range hood and exterior ventingeaoften missed
—
Flooringsf
—
Recessed lightingea
—
Under-cabinet lightingallow
—
Dedicated circuits and GFCIallowoften missed
—
Plumbing rough and trimea
—
Pantry build-outea
—
Paintsf
—
Open wall to living area, with beamea
—
▶Bathroom 1 sf0 / 17—
TaskQtyEst. priceCost
Demo to studsea
—
Plumbing rough-in — supply and wasteea
—
Shower waterproofing and panea
—
Tile shower surround, full heightea
—
Replace tubea
—
Convert tub to walk-in showerea
—
Frameless shower glassea
—
Floor tilesf
—
Vanity with topea
—
Faucet and shower trimea
—
Toiletea
—
Mirror or medicine cabinetea
—
Vanity and ceiling lightingea
—
Exhaust fan vented to exterioreaoften missedCode requires exterior venting — a fan into the attic fails inspection.
—
Towel bars, hooks, paper holderallow
—
Paintsf
—
Shower niche and benchea
—
▶Bathroom 2 sf0 / 17—
TaskQtyEst. priceCost
Demo to studsea
—
Plumbing rough-in — supply and wasteea
—
Shower waterproofing and panea
—
Tile shower surround, full heightea
—
Replace tubea
—
Convert tub to walk-in showerea
—
Frameless shower glassea
—
Floor tilesf
—
Vanity with topea
—
Faucet and shower trimea
—
Toiletea
—
Mirror or medicine cabinetea
—
Vanity and ceiling lightingea
—
Exhaust fan vented to exterioreaoften missedCode requires exterior venting — a fan into the attic fails inspection.
—
Towel bars, hooks, paper holderallow
—
Paintsf
—
Shower niche and benchea
—
▶Bedroom 1 sf0 / 17—
TaskQtyEst. priceCost
Paint walls and ceilingsf
—
Refinish existing hardwoodsf
—
New luxury vinyl planksf
—
New engineered or solid hardwoodsf
—
Carpet and padsf
—
Baseboard and casinglf
—
Interior door, jamb and hardwareea
—
Closet doorsea
—
Closet organiser systemea
—
Recessed LED lightingea
—
Ceiling fixture or fanea
—
Outlets, switches and platesea
—
Drywall patch and repairallow
—
Drywall hang and finishsf
—
Popcorn ceiling removal and smoothsf
—
Wall and ceiling insulationsf
—
Blinds or window coveringsea
—
▶Bedroom 2 sf0 / 17—
TaskQtyEst. priceCost
Paint walls and ceilingsf
—
Refinish existing hardwoodsf
—
New luxury vinyl planksf
—
New engineered or solid hardwoodsf
—
Carpet and padsf
—
Baseboard and casinglf
—
Interior door, jamb and hardwareea
—
Closet doorsea
—
Closet organiser systemea
—
Recessed LED lightingea
—
Ceiling fixture or fanea
—
Outlets, switches and platesea
—
Drywall patch and repairallow
—
Drywall hang and finishsf
—
Popcorn ceiling removal and smoothsf
—
Wall and ceiling insulationsf
—
Blinds or window coveringsea
—
▶Bedroom 3 sf0 / 17—
TaskQtyEst. priceCost
Paint walls and ceilingsf
—
Refinish existing hardwoodsf
—
New luxury vinyl planksf
—
New engineered or solid hardwoodsf
—
Carpet and padsf
—
Baseboard and casinglf
—
Interior door, jamb and hardwareea
—
Closet doorsea
—
Closet organiser systemea
—
Recessed LED lightingea
—
Ceiling fixture or fanea
—
Outlets, switches and platesea
—
Drywall patch and repairallow
—
Drywall hang and finishsf
—
Popcorn ceiling removal and smoothsf
—
Wall and ceiling insulationsf
—
Blinds or window coveringsea
—
▶Living Room sf0 / 11—
TaskQtyEst. priceCost
Paint walls and ceilingsf
—
Refinish existing hardwoodsf
—
New flooringsf
—
Baseboard and casinglf
—
Recessed lightingea
—
Fireplace surround and mantelea
—
Drywall patch and repairallow
—
Drywall hang and finishsf
—
Popcorn ceiling removal and smoothsf
—
Built-in shelving or benchallow
—
Outlets, switches and platesea
—
▶Dining Room sf0 / 7—
TaskQtyEst. priceCost
Paint walls and ceilingsf
—
Refinish existing hardwoodsf
—
New flooringsf
—
Baseboard and casinglf
—
Pendant or chandelierea
—
Drywall patch and repairallow
—
Popcorn ceiling removal and smoothsf
—
▶Laundry sf0 / 6—
TaskQtyEst. priceCost
Washer and dryer hookupsea
—
Dryer vent to exterioreaoften missed
—
Cabinets and counterallow
—
Flooringsf
—
Paintsf
—
Door and hardwareea
—
▶Hallways & Stairs sf0 / 7—
TaskQtyEst. priceCost
Paint walls and ceilingsf
—
Flooringsf
—
Baseboard and casinglf
—
Stair rebuild or re-treadea
—
Railing and balustradelf
—
Hall and stair lightingea
—
Linen closet and doorsea
—
▶Garage sf0 / 6—
TaskQtyEst. priceCost
Garage door and openerea
—
Floor coatingsf
—
Drywall and paintsf
—
Lighting and outletsallow
—
EV charger circuit, 240Vea
—
Slab repair or poursf
—
▶Roof & Gutters0 / 8—
TaskQtyEst. priceCost
Comp shingle — tear off and replacesf
—
Flat roof — torch-down or TPOsf
—
Tile or slate roofsf
—
Sheathing replacementsfoften missed
—
Gutters and downspoutslf
—
Skylightsea
—
Flashing, vents and detailallow
—
Chimney repair or removalallow
—
▶Exterior & Curb Appeal0 / 9—
TaskQtyEst. priceCost
Exterior paint — prep and paintsf
—
Stucco patch and re-coatallow
—
Siding repair and replacementallowAlternative to stucco — pick whichever the house actually has.
—
Dry rot and termite damage repairallowoften missedA near-certainty on anything pre-1970 in the Bay Area.
—
Entry doorea
—
Porch and front stepsallow
—
Exterior trim and fasciaallow
—
Pressure washallow
—
House numbers, lighting, hardwareallow
—
▶Structural & Foundation0 / 9—
TaskQtyEst. priceCost
Seismic retrofit — foundation boltinglfoften missedStandard on Bay Area pre-1980 stock and often an insurance condition.
—
Cripple wall bracing and shearlf
—
Foundation crack repairallow
—
Foundation replacementsf
—
Pier and beam repair, post replacementallow
—
Subfloor repair and replacementsf
—
Joist sistering and floor structureallow
—
Beam for load-bearing wall removalea
—
Perimeter drainage and French drainlfoften missed
—
▶Electrical — whole house0 / 9—
TaskQtyEst. priceCost
Main panel upgrade to 200Aeaoften missed
—
Service drop and utility coordinationea
—
Whole-house rewiresf
—
Partial rewire and added circuitsallow
—
Knob-and-tube removalsfoften missedCommon pre-1950 and a blocker for insurance and lending.
—
Subpanelea
—
GFCI and AFCI protectionallow
—
Smoke and CO alarms to codeallowoften missed
—
Solar PV systemallow
—
▶Plumbing — whole house0 / 9—
TaskQtyEst. priceCost
Whole-house repipesf
—
Galvanised supply replacementallow
—
Sewer lateral replacementlfoften missedOakland, Berkeley, Albany and Piedmont require a certificate at sale.
—
Sewer lateral compliance certificateeaoften missed
—
Drain and waste line replacementallow
—
Water heater with seismic strappingea
—
Tankless conversionea
—
Gas line work and seismic shutoffallow
—
Exterior hose bibsallow
—
▶HVAC0 / 7—
TaskQtyEst. priceCost
Furnace replacementea
—
Condenser and coilea
—
Heat pump — full changeoutea
—
Ductless mini-split, per headea
—
New ductwork throughoutsf
—
Duct sealing and Title 24 testingallowoften missed
—
Smart thermostatea
—
▶Windows & Doors0 / 5—
TaskQtyEst. priceCost
Vinyl retrofit windows, dual paneea
—
New-construction windows with patchea
—
Sliding or French patio doorea
—
Window screensea
—
Window trim and sillsallow
—
▶Landscaping & Yard0 / 12—
TaskQtyEst. priceCost
Front yard refresh — clean, mulch, plantallowHighest-return dollar in the whole budget.
—
Sod and soil prepsf
—
Drought-tolerant planting and gravelsfAlternative to sod. Cheaper to keep alive through a long marketing period.
—
Irrigation and controllerallow
—
Fencinglf
—
Gatesea
—
Deck build or re-decksf
—
Patio — pavers or stamped concretesf
—
Retaining walllf
—
Tree removal and trimmingallow
—
Driveway replacementsf
—
Exterior and landscape lightingallow
—
▶Demolition & Site0 / 7—
TaskQtyEst. priceCost
Interior strip-outsf
—
Flooring removal and disposalsf
—
Dumpsters — 30 yard, per pulleaoften missed
—
Debris hauling and labourallow
—
Asbestos abatementallowoften missedAssume it on anything pre-1980 until tested.
—
Lead paint remediationallowoften missed
—
Temporary fencing and site protectionallow
—
▶Permits & Soft Costs0 / 13—
TaskQtyEst. priceCost
Building permiteaoften missed
—
Electrical, plumbing and mechanical permitsallow
—
Plan check and city reviewea
—
Architect — drawings and permit setallow
—
Structural engineer and calcsallow
—
Title 24 energy complianceeaoften missed
—
Survey and site planea
—
Portable toilet and site sanitationallow
—
Temporary power and utilitiesallow
—
Final construction cleanallow
—
General contractor fee% of hardPercent of every hard cost above.
—
—
General conditions — supervision, tools, delivery% of hard
—
—
Contingency% of hardoften missedThe line that saves deals. 10% cosmetic, 15–20% on a gut.
—
—
Rehab estimate$0$0/sf
Tasks0

Prices are shared across every deal — correct one after a real bid and every future underwrite is right. What this deal owns is which tasks are scoped, each room's area, and any quantity you override. Pushing sets your base rehab scenario; low and high stay yours, since they are judgement about risk rather than arithmetic.

Screening estimates only — verify every figure locally before making an offer. Transfer tax and property tax presets carry the date they were verified; rates change by ballot measure, so confirm before relying on them. Property tax assumes Prop 13 reassessment to the purchase price. Every profit figure here is before income tax — a flip is ordinary income and also owes self-employment tax, which the Income Tax Calculator models separately, along with the §121 exclusion a live-in flip is chasing.